Key takeaways
- Build the book in a fixed order: tasks, definitions, time standards, labor rate, materials, overhead and margin, then options.
- Time standards come from your own job history, using typical times rather than your best tech’s record.
- Labor is the biggest input and it varies by employer: plumbers at plumbing, heating and AC contractors had a median wage of $63,010 in May 2025[1].
- Start with the 30 to 50 tasks that make up most tickets; a small accurate book beats a large guessed one.
- Review prices on a schedule, because labor and material costs keep moving[2].
What a price book is for
A price book turns every common plumbing task into a written price that any tech can quote the same way. It protects margin, speeds up quoting at the door and gives customers one number before the work starts. It is also the foundation of flat-rate pricing; if you are still deciding between models, start with flat rate vs time and materials.
Commercial books exist, and many shops start from one. Building your own, or at least rebuilding a bought one with your numbers, is worth it because every input is local: your wages, your overhead, your supply-house costs, your techs’ speed and your market. The order below matters, because each step depends on the one before.
The build order
List the tasks
Export twelve months of invoices and count how often each kind of job appears. The top 30 to 50 tasks usually cover most service tickets. Start there.
Define each task
Write what is included and what is not: removal and disposal, permits, shutoff valves, testing, clean-up, and the access assumption, such as no wall opening.
Set time standards
From your job records, find the typical time for each task, including setup, the work, testing and clean-up. Use the middle of the range, not the fastest job.
Calculate the billable labor rate
Turn wages, payroll costs and unbillable time into the cost of one billable hour, then add overhead and profit. Details are in the labor rate guide.
Price the materials
List the parts for each task at current cost from your supplier, then apply your markup method consistently.
Assemble and round
Price equals time standard multiplied by billable rate, plus marked-up materials, plus any task-specific extras such as disposal. Round to clean numbers.
Add options and add-ons
For key tasks, write good, better and best versions and common add-ons such as a new shutoff valve or an expansion tank.
Test before launch
Re-price thirty past jobs with the new book and compare with what you actually charged and earned. Investigate any large gaps.
Train and launch
Teach techs to find tasks quickly and explain the price. Launch on a set date and collect questions for the first month.
Task definitions prevent most disputes
Most price-book arguments are really scope arguments. A customer hears “toilet replacement” and assumes the new supply line, wax ring, closet bolts, disposal of the old toilet and a caulk bead are included. If your task includes them, say so. If not, list them as add-ons.
| Part of the task card | Example wording |
|---|---|
| Task name | Replace standard floor-mounted toilet, customer-approved model |
| Includes | Remove and dispose of old toilet, new wax ring and bolts, new supply line, set and level, leak test, clean-up |
| Excludes | Flange repair, subfloor repair, shutoff valve replacement, moving the drain |
| Assumes | Accessible bathroom, working shutoff, flange in serviceable condition |
| Common add-ons | Quarter-turn shutoff valve, flange repair ring, comfort-height upgrade |
Write these cards once and reuse the wording on estimates and invoices. Customers see the same language from quote to final paperwork, which builds trust.
Time standards from your own data
Time standards decide whether the book makes money. Pull actual on-site times for each task from your scheduling system or time cards, remove outliers caused by unusual conditions, and take the typical value. If you have little data, time the next ten instances of each top task.
- Include setup, protection of floors, testing and clean-up. Techs often remember only the wrench time.
- Exclude drive time if you charge a separate trip or diagnostic fee; include an allowance if you do not.
- Keep separate standards where conditions differ a lot, such as a water heater in a garage versus one in an attic.
- Revisit standards after training or new tools. If the shop gets faster, you can choose to keep the margin or lower the price.
Labor: the biggest input
Wage levels differ by employer type and market. In May 2025 the median wage for plumbers, pipefitters and steamfitters was $63,800 overall, $63,010 for those working at plumbing, heating and AC contractors and $71,660 in government, against $58,150 for all construction trades and $50,980 for all occupations[1]. Your own payroll is the number to use, but the spread shows why copying another shop’s rates is risky.
Wages are only part of labor cost. Across private industry, benefits were 30.0% of employer compensation costs in June 2026[3], and average annual payroll per employee at plumbing, heating and AC contractors was about $73,700 in 2023[4]. Then come unbillable hours: drive time, meetings, training and callbacks. The billable labor rate guide walks through the full calculation, and the overhead guide covers the costs that sit on top.
Materials, overhead and margin
Price materials at what you pay now, not what you paid when you last ordered. Choose one markup method, such as a sliding scale that applies a higher percentage to low-cost parts, and apply it the same way across the book. Write the method down so whoever maintains the book next year can repeat it.
Overhead and profit can be built into the billable hourly rate or added as a separate line. Building them into the rate is simpler and keeps every task consistent. Whichever way you choose, check the result against the industry’s cost structure: payroll equalled about 27% of receipts at plumbing, heating and AC contractors in 2022[5]. If your book implies payroll is a much larger share of each ticket, margin is probably too thin.
Example (fictional): billable rate $170 an hour including overhead and profit; time standard for a kitchen faucet replacement 1.25 hours, so labor is $212.50. Mid-grade faucet and supply lines cost $160 and, with the shop’s markup, price at $256. Task price before rounding: $468.50, listed at $469 with a better option and a premium option beside it.
Margin math errors are common at this step, especially confusing markup with margin. Check your formulas against markup vs margin before you publish the book.
Trip fees, minimums and after-hours
Decide three policies before the book goes live, because they change every task price. First, whether you charge a separate trip or diagnostic fee, and whether it is credited toward the repair. Second, whether there is a minimum ticket, so a five-minute fix still covers the truck roll. Third, how after-hours, weekend and emergency work is priced: a multiplier on the task price, a fixed surcharge or a separate after-hours book.
Write each policy in one sentence that the office can read to a caller and the tech can repeat at the door. Policies that cannot be explained simply tend to be applied inconsistently, which is how disputes start. For the trip-fee question in detail, see the guides on diagnostic fees and free estimates in this cluster.
Price book mistakes to avoid
- Pricing from a competitor’s website. You inherit their costs and mistakes, not yours.
- Using the fastest tech’s time as the standard, so every average job loses money.
- Leaving disposal, permits and shutoff valves out of task definitions, then arguing about them at the door.
- Too many tasks too soon. Hundreds of rarely used tasks are hard to maintain and slow to search.
- No owner. Someone must be responsible for updates, or the book drifts out of date within months.
- Never checking results. Compare gross margin by task every quarter to see which prices are working.
Keeping the book current
A price book starts aging the day it is published. Average hourly earnings at plumbing, heating and AC contractors rose from $40.59 to $42.38 in the year to September 2026[2], and material prices move faster than that in some categories. Set a maintenance routine:
- Monthly: update the cost of the twenty most-used parts and anything with a known supplier increase.
- Quarterly: compare actual times with time standards for the top tasks, and adjust any that drift.
- Yearly: recalculate the billable labor rate after wage reviews and insurance renewals, then re-price the whole book.
- Any time: add a task when the same unlisted job appears several times in a month.
Record every change with a date and reason. When a customer asks why a price differs from last year, the office can explain it plainly, and when the book needs a full rebuild, you have the history to do it quickly.
Frequently asked questions
How many tasks should a plumbing price book have?
Start with the 30 to 50 tasks that make up most of your service tickets, priced carefully. Add tasks as the same unlisted jobs keep appearing. A smaller accurate book is more useful than a large one built on guesses.
Should I buy a price book or build my own?
A purchased book can save time on task lists and definitions, but rebuild the numbers with your own wages, overhead, supplier costs and job times. Those inputs are local and change the price more than the template does.
How often should plumbing prices be updated?
Update high-use material costs monthly, review time standards quarterly and recalculate the labor rate and full book at least once a year, or sooner when costs jump.
References
U.S. Bureau of Labor Statistics (2025). Occupational Outlook Handbook: Plumbers, Pipefitters, and Steamfitters (opens in a new tab) ↑
U.S. Bureau of Labor Statistics, Current Employment Statistics (2026). Average hourly earnings of all employees, plumbing, heating, and air-conditioning contractors, not seasonally adjusted (CEU2023822003) (opens in a new tab) ↑
U.S. Bureau of Labor Statistics (2026). Employer Costs for Employee Compensation - June 2026 (opens in a new tab) ↑
U.S. Census Bureau (2023). County Business Patterns 2023, U.S. national file (cbp23us) (opens in a new tab) ↑
U.S. Census Bureau (2022). Statistics of U.S. Businesses 2022: U.S. and states, 6-digit NAICS (opens in a new tab) ↑