Key takeaways
- Build the bid from a fixture unit that covers underground, rough-in, top-out and trim, plus per-foot items that are not fixtures.
- Tie the draw schedule to inspections and phases so each payment matches work the builder can see.
- Expect retainage; federal construction contracts cap it at 10%, and private contracts vary, so price the cash it ties up.
- Clear qualifications and exclusions protect your margin more than a higher unit price.
Know the market you are bidding into
New construction work rises and falls with housing. US housing starts ran at a seasonally adjusted annual rate of 1,221,000 in September 2026, 7.4% below a year earlier, with single-family starts at 859,000[1]. Total construction spending was running at $2,186.1 billion a year, 2.7% below September 2025[2]. When starts slow, builders squeeze subcontractor prices and more plumbers chase fewer bids.
Source: U.S. Census Bureau, 2026[1]
Show the data
| Item | Value |
|---|---|
| All privately-owned starts | 1,221 thousand units |
| Single-family starts | 859 thousand units |
The plumbing scope still matters to builders. NAHB found that major system rough-ins, meaning plumbing, electrical and HVAC together, made up 19.2% of the cost of building a new home in 2024[3]. BLS expects plumber demand to come both from new construction and from maintaining existing buildings[4], which is why many shops balance construction work with service to smooth the cycle.
Build the fixture unit
Most residential new construction is bid per fixture, with separate prices for items that do not fit the fixture count. The per-fixture number must carry every phase of work for that fixture, not just the rough-in.
Define the fixture
List what counts as one fixture: toilet, lavatory, tub, shower, kitchen sink, laundry box, hose bib, water heater connection, dishwasher and ice maker connections. Decide whether connections count as half fixtures.
Time each phase
From your job cost records, take labor hours per fixture for underground, rough-in, top-out and trim. Use the median of recent comparable houses.
Price materials per fixture
Pipe, fittings, valves, supports and nail plates for a typical run, at today's supplier quote, with a waste allowance.
Add per-foot and per-house items
Water service, sewer lateral, gas piping, water heater, permits, inspections and any pump or backflow device.
Load labor and add overhead
Apply your loaded labor rate, then overhead and margin, so each fixture carries its share of trucks, supervision and office.
Check against completed jobs
Compare your total for a plan with what similar houses actually cost you, and adjust before sending.
| Bid component | Basis | Notes |
|---|---|---|
| Fixtures | Count from plans times per-fixture price | Include rough-in, top-out and trim labor |
| Water service | Per foot from meter to house | Depth, material and trenching responsibility |
| Sewer lateral | Per foot to the tap or cleanout | Who excavates and backfills |
| Gas piping | Per outlet or per foot | Sizing for tankless or high-input appliances |
| Water heater | Per unit, by type | Venting, pan and expansion tank where required |
| Permits and inspections | Actual fees plus admin time | Re-inspection fees as an exclusion or allowance |
| Fixtures supplied | By builder or by plumber | Markup and handling if you supply |
Example (fictional): a builder's 2,400-square-foot plan has 18 fixtures. The shop's per-fixture price is $585, giving $10,530. Water service at 60 feet, sewer lateral at 45 feet, gas piping to four outlets, a standard water heater and permits add $5,940. The bid totals $16,470, with fixtures supplied by the builder and trenching excluded.
Production builders, custom homes and multifamily
The same per-fixture method needs different settings depending on the customer. Production builders repeat a handful of plans across a subdivision, so your crews get faster on each plan and your bid can reflect that learning, but the builder will expect you to share it through a lower price. Custom homes are the opposite: every house is new, specifications change during the build and the homeowner may make decisions late. Multifamily jobs bring stacked layouts, fire separations, longer schedules and usually stricter retainage and paperwork.
- Production: price per plan, with options priced separately, and a clear rule for when a plan revision means a new price.
- Custom: add a contingency or allowance for late decisions, and be strict about change orders from the start.
- Multifamily: price supervision and coordination time explicitly, and plan cash for longer draw cycles and retainage.
Read the plans for what is not a fixture
- Long horizontal runs in slab-on-grade houses, or runs through engineered joists that need special supports.
- Fire separation and penetrations that need firestopping.
- Recirculation lines, pressure-reducing valves and expansion tanks the local code requires.
- Outdoor kitchens, pool equipment, irrigation tie-ins and garage sinks that are easy to miss on the drawings.
- Basement bathroom rough-ins for future finish, which still need underground and venting.
- Specifications that call for specific brands or materials different from your standard.
Mark each of these on the plan set and price them separately. A bid that hides them in the fixture price will lose money on the houses that have them.
Set a draw schedule by phase
A draw schedule tells the builder when you will bill and how much. Tie each draw to a phase the builder can see and an inspection where possible.
- Underground: billed when the underground passes inspection and the slab or crawl space work can proceed.
- Rough-in and top-out: billed when the rough-in passes inspection, usually the largest draw.
- Water heater and gas: billed when set and tested, if not part of rough-in.
- Trim and final: billed when fixtures are set and the final inspection passes.
- Retainage release: billed when the house closes or the contract's release condition is met.
Weight each draw to match the work and materials in that phase, not to front-load the money. Builders spot front-loaded schedules quickly, and lenders that fund construction draws often check them too.
Retainage
Retainage is the part of each payment the owner or builder holds back until the work is complete. On federal construction contracts, the Federal Acquisition Regulation says the amount retained shall not exceed 10% of the approved estimated amount, and that it may be adjusted as the job nears completion to recognize better than expected performance[5]. Private contracts set their own terms, and many states have laws that limit retainage or set deadlines for releasing it.
- Read the retainage clause before bidding: the percentage, when it reduces and what triggers release.
- Price the cash it ties up. Retainage withheld across many houses can equal several weeks of payroll.
- Ask for a reduction once the job is half complete, or release per house rather than per project.
- Bill retainage separately and on time; it is often forgotten by both sides.
- Learn your state's retainage and prompt payment rules for private work.
Qualifications and exclusions
Your bid is only as safe as its assumptions. Put them in writing on the bid itself, and attach your change order terms so the builder knows how changes are handled.
- Plans and revision date the bid is based on.
- Who supplies fixtures, water heaters and appliances.
- Excavation, backfill, concrete cutting and patching responsibilities.
- Number of trips per phase included; extra trips caused by schedule changes are billed.
- Re-inspection fees caused by other trades.
- Price validity period and material escalation terms.
Changes on construction jobs follow the same discipline as service work; see change orders on plumbing jobs for the process and paperwork.
Review the bid before it goes out
- Fixture count checked by a second person against the plans.
- Per-foot items measured from the site plan, not guessed.
- Supplier quote dated within the last few weeks for the main materials.
- Permit and inspection fees confirmed for that jurisdiction.
- Draw schedule attached and weighted to the work.
- Retainage terms read and their cash cost included.
- Qualifications, exclusions and validity period printed on the bid.
A ten-minute review catches the errors that cost the most: a missed bathroom, a wrong revision date or a gas run priced at half its length.
Choose builders as carefully as they choose you
A low-margin bid with a builder who pays on time and keeps the site ready can beat a higher price with one who does neither. Before committing to a builder or a subdivision, check how fast they pay draws, how they handle changes, whether their supers keep the schedule and how many trips your crews will make per house. Then track every house: bid hours versus actual hours by phase, materials versus estimate and days from draw request to payment. Those numbers tell you what to change in the next bid and which builders to keep. Callbacks after closing belong in the price too; our guide to building warranty costs into prices shows a method.
Frequently asked questions
How do I count fixtures for a bid?
List what counts as one fixture and what counts as a half fixture, then count from the plans. Items like water service, sewer lateral and gas piping are priced separately.
What is a normal retainage amount?
It depends on the contract and state law. Federal construction contracts cap it at 10% of the approved estimated amount; private contracts vary.
Should I front-load my draw schedule?
No. Weight draws to the work and materials in each phase. Builders and lenders notice front-loading, and it damages trust.
How do I protect against material price increases?
State a price validity period and an escalation clause for named materials on the bid, and update supplier quotes before signing.
References
U.S. Census Bureau (2026). New Residential Construction, September 2026 (opens in a new tab) โ
U.S. Census Bureau (2026). Monthly Construction Spending, September 2026 (opens in a new tab) โ
National Association of Home Builders (Eye On Housing) (2024). Cost of Constructing a Home in 2024 (opens in a new tab) โ
U.S. Bureau of Labor Statistics (2025-2035). Occupational Outlook Handbook: Plumbers, Pipefitters, and Steamfitters (opens in a new tab) โ
Acquisition.gov (Federal Acquisition Regulation) (2026). FAR 32.103 Progress payments under construction contracts (opens in a new tab) โ